<para>The distribution to be used during scheduling</para><para>If distribution is 'None', the tasks estimate is used as is during scheduling.</para><para>If distribution is 'PERT', the estimate used is calculated based on the entered optimistic- (O), pessimistic-(P) and most likely (M) estimate. The formula used for this is (O + 4 * M + P) / 6.<para>