The system creates messages while performing processes. In this window you can view them.
MRP Notice
It is a group of messages generated for the MRP process. It indicates to the scheduler the actions he needs to do to reach the Master Production Schedule. The action messages are set as notices for the planner when he sign up the Compiere session.
The possible action messages are:
MRP Code
[tab]
Action Message
MRP - 001
[tab]
Beginning Quantity Less Than Zero.
MRP - 020
[tab]
Create - A Supply Order should be created to satisfy a negative projected on hand balance.
This message is only generate if Create Plan is No or if a new requirement appears the time fence.
MRP - 030
[tab]
De Expedite - Indicates that a scheduled supply order is due before it is needed
and should be delayed, or demand rescheduled to an earlier date.
MRP - 040
[tab]
Expedite - Indicates that a scheduled supply order is due after is needed
and should be rescheduled to an earlier date, or demand rescheduled to a later date.
MRP - 050
[tab]
Cancel - Indicate that a scheduled supply order is no longer needed and should be deleted.
MRP - 060
[tab]
Release Due For - Indicate that a schedule order should be released.
MRP - 070
[tab]
Release Past Due For - Indicate that a supply order was not released when it was due,
and should be either released or expedited now, or the demand rescheduled for a later date.
MRP - 080
[tab]
Quantity Less than Minimum - Indicates that a supply order was created for
a quantity less than the minimum quantity set in the product planning
MRP - 090
[tab]
Quantity Less than Maximum - Indicates that a supply order was created for a quantity
for a quantity greater than than maximum quantity set in the product planning
MRP - 100
[tab]
Past Due Time Fence - Indicates that there is an unsatisfied material requirement inside
the planning time fence for this item. You should either manually schedule and expedite orders to
fill this demand or delay fulfillment of the requirement that created the demand.
MRP - 110
[tab]
No exists Dem